Bhadbhut Barrage Project

One More Initiative Towards Creating Water-Rich Gujarat
Bhadbhut Barrage of Length 1648m with 90 Gates, Six-Lane Bridge over Barrage & 20 km long Flood Protection Embankments with Service Roads on both banks.

About The Project

Bhadbhut Barrage Project located near village Bhadbhut taluka & district Bharuch envisages constuction of Barrage cum Bridge structure and Flood protection embankments on left & right banks of the river Narmada. Hon'ble Prime Minister of India laid the foundation stone of the Project. The project construction work was awarded to the agency M/s DBL-HCC (JV), Bhopal on EPC bases. The work is in Progress.

Cost of EPC works - INR 4167.69 Cr.
Date of Start - 15th October 2020
Duration - 4 years + Operation & Maintenance of 10 years

Project Components (% Cost)

Progress at a Glance

Component Wise Work Progress